Practice Update

Proper planning is the cornerstone of hurricane preparedness. With 11 named storms, four hurricanes, and two major hurricanes expected this season, it is imperative that every construction project within the State of Florida have a hurricane plan in place. Ideally, every construction project should have a hurricane plan incorporated into the written contract between the owner and the contractor, and the plan should then be incorporated into each lower tiered subcontract on the project.

The hurricane plan should be agreed upon by the primary project participants, including the owner, lead design professionals and general contractor. It should address a wide range of issues that could arise prior to, during, and after a hurricane, and should contain provisions to ensure personal safety, minimize property damage, accidents and downtime on the project. No two projects are exactly alike and the plan should therefore be tailored to incorporate the specific project’s details and requirements. Consultation with an attorney who specializes in construction contracts may be helpful in drafting a plan appropriate for the project. Additionally, because the scope and design of a project tend to change over time, the plan should be re-evaluated by the entire project team should any substantial revisions to the project occur.

In developing a given project’s hurricane plan, the plan should contain individual phases, each outlined such that the appropriate actions and responsibilities during various stages of a hurricane event are clearly set forth. Moreover, each project team participant should have a representative designated to ensure proper plan compliance. Plan flexibility is also important because history has proven that the nature and conditions of each storm may vary significantly. As a general rule, the plan’s phases should consist of the pre-hurricane procedures stage, the pre-evacuation stage (coastal areas), the hurricane watch and warning stages, and the post-hurricane procedures stage.

Pre-Hurricane Procedures Stage

During the first stage every team participant should submit emergency contact information, identify key personnel responsible for implementing the plan, identify evacuation procedures and order additional hurricane supplies to be available on the project prior to the hurricane season. The foregoing exchange of information can be put together in the form of an Emergency Contact List and should be distributed to key team members at the outset of the project and then updated and redistributed as the information changes during the course of the project.

Pre-Evacuation Stage (Coastal Areas)

The pre-evacuation stage typically commences once a Tropical Storm Warning or Hurricane Alert becomes effective or is believed to be imminent. At this stage, the project’s key personnel should be monitoring the news alerts regularly and begin making preparations to evacuate all nonessential personnel. All shipments and deliveries of non-essential materials for the project should be halted. If there appears to be a strong likelihood of hurricane conditions in the area of the project, all construction documents, records, files and computers should also be moved off site or appropriately stored, and the project as a whole should be secured, including the removal or safe storage of any building materials which could become projectiles.

Hurricane Watch and Warning Stage

When hurricane conditions are expected within 24-48 hours, the plan should progress to the hurricane watch and warning stages. We all know that loose material, such as 2x4’s, rebar, scaffolding and roof tile can become dangerous projectiles. Depending on the size of the project, and the manpower available at the time, one general contractor might be able to properly secure all of these items within 24 hours, while another will need two or more days to accomplish that same goal. In either case, by the conclusion of the Hurricane Warning Stage, the site should be fully secured, power should be disconnected and a recovery team should be in place and available to return to the project once conditions have subsided and it is safe to return. It is also a good idea, for insurance claim purposes, to make a video or photographic record of the site in its pre-storm condition.

Post Hurricane Procedure Stage

The post hurricane procedure is the last stage of the plan and should begin as soon as persons may safely return to the site. A complete project assessment should be conducted by the recovery team accompanied by a damage report. The damage report should include pictures and/or video of the project and neighboring property if affected and the applicable insurance adjusters should be immediately notified. Lastly, all project team representatives should be notified of the status and advised when they can mobilize onto the site to begin clean up and recommence construction.

Additional information should also be included in the plan such as definitions of hurricane related terms, emergency and applicable project phone numbers, contact information and storm tracking sources and websites. With the extensive damage and attendant complications experienced during last year's hurricane season, and because preparation is the best protection, every Florida construction project should have an establish hurricane plan in place prior to June 1st.

This update has been revised and was originally published in the Daily Business Review on June 14, 2007.

People
Perspectives
Work
Firm
Vision
To navigate our site
To search our site

Welcome to our new site

Click anywhere to enter